Connecting the incoming and outgoing lines

All lines must be connected in accordance with the applicable standards and specifications and tested with purge gas (pressure test and leak test). The specifications on dimensioning of the connections are described in the "Design" chapter.

  1. Connect the purge gas source to the purge gas inlet of the pressure control panel. It must be ensured that there is a purge gas pressure of 6 to 10 bar on valve PGI (standard for SP4 and SP6 only).
  2. Connect the waste gas outlets of the pressure control panel to the waste gas lines.
  3. Connect the process gas outlet of the pressure control panel to the process.