Putting the pressure control panel into a safe condition
In the event of interruptions in operation for more than 48 hours or pending maintenance or servicing, the pressure control panel must be put into a safe condition.
The process gas source must be connected during flushing (see "Connecting the process gas source"). Also observe the "Preparations for commissioning" chapter.
- Close process gas source and route off the acetylene located in the pressure control panel via the connected consumers.
- When this pressure relief or routing-off process is completed, the two pressure gauges on the pressure regulator must display the value "zero". Visual inspection!
- Close PLI.
- Close pilot pressure source valve.
- Vent the pilot pressure on the switching panel by pressing the switching lever up and down on both anti-tip roller valves.
- Vent the pilot gas pressure regulator.
- Detach the control pressure connection.